Latest Power Supply Procurement Plan (PSPP) of TEI and information on ongoing and completed bids.
Competitive Selection Process
The conduct of CSP is governed by DOE Department Circular No. DC2023-06-0021 and ERC Resolution No. 16, Series of 2023 which took effect on 19 July 2023 and 23 October 2023. This site contains the latest Power Supply Procurement Plan (PSPP) of TEI and information on ongoing bids.
Good to know
For Inquiries
Kindly email the BAC-Secretariat of TEI's Bids and Awards Committee for power supply agreements at bac-secretariat@teiph.com
DOE Circular
Prescribing the Policy of the Mandatory Conduct of the Competitive Selection Process by Distribution Utilities for the Procurement of Power Supply for their Captive Market.
Effectivity
Took effect on 19 July 2023
ERC Resolution
Implementing Guidelines for the Procurement, Execution, and Evaluation of Power Supply Agreements Entered into by Distribution Utilities for the Supply of Electricity to their Captive Market.
Effectivity
Took effect on 23 October 2023
Procurement Plan
Current and completed bids under TEI's Competitive Selection Process for power supply agreements.
10MW Supply from 26 December 2026 to 25 December 2041 with escalation in contracted capacity as presented below.
Period From
Period To
Contracted Capacity (MW)
26-Dec-26
25-Dec-27
10
26-Dec-27
25-Dec-28
15
26-Dec-28
25-Dec-31
20
26-Dec-31
25-Dec-41
25
Updates
Documents
Documents